Most businesses considering rooftop solar in Dubai expect the most difficult and time-consuming part of the project to be installing solar panels.
It is not. The equipment is well understood and the installation is a few weeks of work. The part that determines whether your project runs to schedule is the approvals process, and it is the part that gets least attention at proposal stage.
Here is what that process actually involves, what it needs from you at each stage, and where projects get held up.
Note: this article covers systems connected under DEWA's Shams Dubai programme, which is the route for the large majority of commercial rooftop installations in Dubai. Businesses in manufacturing, data centres or agri-tech may qualify for DEWA's D33 policy, which has a different application route and a different set of prerequisites. If you are in one of those three categories, see our post on DEWA's D33 policy before you go any further, because it changes both the capacity you can install and the way your exported power is valued.
The thing to understand before anything else
A Shams Dubai based solar PV system cannot be installed and then connected. It has to be approved, then installed, then inspected, then energised, in that order.
That sounds obvious written down, and it is the single most common misunderstanding we encounter. Businesses occasionally receive proposals that treat approval as a formality to be sorted out alongside the works, or worse, afterwards. A system installed without approval is not a solar system. It is an unconnected array on your roof and a problem to unwind.
The second thing to know: the work has to be carried out by a contractor and consultant enrolled with DEWA for solar. This is not a quality badge you can choose to ignore, it is a condition of the connection. If a quotation looks unusually attractive, confirming enrolment is the first thing worth checking. Solaroofing is a registered DEWA solar contractor.
Stage 1: Feasibility, and the number that governs it
Before any application, three numbers need establishing: your roof area, your total connected load, and your actual consumption.
Roof area determines physical fit. Total connected load determines what DEWA will permit, because installed capacity under Shams Dubai cannot exceed the applicable share of your plot's total connected load. Consumption determines what is economically sensible, since exported surplus becomes credits against future bills rather than a payment.
Whichever of the three is smallest governs your system. Our post on total connected load explains where to find yours and why proposals that skip it tend to be resized downwards at application stage, taking the savings figures with them.
This is also the stage at which the roof itself should be assessed, which we come back to below.
What you need to provide: your latest approved DEWA design approval, your as-built electrical load schedules or single line diagrams, and twelve months of DEWA bills. In leased units these documents sometimes sat with a previous tenant. If you cannot find them, we can help you track them down.
Stage 2: Design and documentation
The system is designed against the constraints established at feasibility, and the application documentation is prepared.
This is engineering work rather than paperwork. The design has to demonstrate how the system connects to your existing electrical infrastructure, how it protects itself and the grid under fault conditions, and how it sits on the roof structurally. The documents go in as a set, and an incomplete set is the most common reason an application comes back.
What you need to provide: site access for survey, your electrical documentation, a decision on system size, signed paperwork that formally identifies the solar contractor hired for the project, and as-built architectural and structural drawings of the building. What we handle: the design, the drawings, the calculations and the submission.
Stage 3: Application and the NOC
The application goes to DEWA, and what comes back, usually within two to four weeks, is a no objection certificate along with a design approval. The NOC is the authorisation to proceed, and it comes before installation rather than after.
It is worth being clear with your own stakeholders about this sequence, because internal schedules are sometimes built on the assumption that the panels arrive first. Equipment procurement can run in parallel, but the works on the roof must wait for the NOC.
What you need to provide: signatures and any information DEWA requests in response to the submission.
Stage 4: Installation
With the NOC in hand, the system is installed.
The relevant point for a metal roof, and the reason this subject belongs on a roofing company's blog, is that mounting a solar array means fixing into or onto the roof. Every mounting point is a point where the roof's watertightness is either maintained or compromised, and it will stay there for twenty-five years.
This is where doing both aspects of the roof transformation project by one company matters. A solar installer treats the roof as a mounting surface. A roofing contractor treats it as a waterproofing system that is about to be penetrated several hundred times. The second view is the one that keeps your building dry.
What you need to provide: roof access, agreed working hours and a point of contact. What happens to your operation: the works are carried out from the roof exterior, so production continues underneath.
Stage 5: Inspection and energisation
DEWA inspects the installed system and, once satisfied, installs a bidirectional solar meter and energises the connection.
From that point, generation offsets your consumption in real time and any surplus is exported and credited against future bills. The credits reduce what you pay rather than being paid out, which is why system size is best matched to consumption. Note that it could take up to three months after energisation for the credits to show up on your DEWA bills, though you would still benefit from solar and the credits are not lost due to that delay.
What you need to provide: access for the inspection.
Stage 6: Monitoring and maintenance
The system is commissioned and handed over with monitoring, which is what tells you whether it is performing as designed. Post-connection, DEWA also requests a power quality, or harmonics, check to be done, after which the project is officially marked as "connected to grid" via a solar connection status report, also referred to as the final interconnection certificate.
System performance monitoring is more important here than in most markets, because the largest controllable loss on a UAE rooftop array is dust. Our post on dust and soiling covers what that costs in output and how cleaning intervals are set from monitoring data rather than from a calendar.
Where projects actually get delayed
Three things, in order of how often we see them.
Capacity discovered at application. A system sized from roof area rather than connected load gets resized when the application goes in, and everything downstream changes with it: the generation figure, the savings figure and the payback the project was approved on. This is entirely avoidable at feasibility.
Missing documentation. Particularly in leased units and older buildings. It is a short task to retrieve, and a long delay if it is discovered late.
Roof condition. The one most often left until last, and the most expensive to find late.
The roof question, properly
If the roof needs waterproofing work, it needs doing before the array goes on. Not after.
Once panels are installed, any remedial work to the roof underneath means removing and reinstating the array, which is a significant cost, a risk to the panels and a risk to every mounting penetration. A roof that was at the end of its life when the panels went up does not get better with an array on top of it and a cleaning crew walking it monthly.
The sequence that works is: assess the roof, do whatever it needs, then install solar onto a roof with a warranty on it. Our post on waterproofing before solar sets out why, and restoration or replacement covers how that condition is judged.
Across the commercial systems we install under Shams Dubai, payback typically falls within four to seven years, after accounting for all costs including permitting fees and operations and maintenance. Doing the roof first does not change that materially. Doing it afterwards can.
Who handles what
Solaroofing has been waterproofing metal roofs in the UAE for over 30 years and designing and installing solar PV since 2019, as a registered DEWA solar contractor. We handle the approvals process end to end, including DEWA, DM, DDA, DIP, JAFZA, Trakhees and DCD, which means all the doubts relating to capacity and roof condition are settled at feasibility rather than discovered at application.
Frequently Asked Questions
Do I need DEWA approval to install solar in Dubai? Yes. A rooftop system connected under Shams Dubai has to be approved before installation, then inspected and energised by DEWA afterwards. The work also has to be carried out by a contractor and consultant enrolled with DEWA for solar, which is a condition of the connection rather than an optional credential. A system installed without approval cannot be connected.
What is the DEWA solar approval process? In sequence: feasibility, where roof area, total connected load and consumption are established; design and preparation of the application documentation; submission to DEWA and issue of a no objection certificate along with a design approval; installation; DEWA inspection and energisation with a bidirectional solar meter; then monitoring, a post-connection power quality check, and the final interconnection certificate. The NOC comes before installation, not after.
How long does DEWA solar approval take? Typically two to four weeks, provided the application is not returned. It varies with the completeness of the submission and with DEWA's own workload, so no single figure applies to every project. Procurement can run in parallel, but works on the roof wait for the NOC.
What documents do I need for a Shams Dubai application? Your latest approved DEWA design approval, your as-built electrical load schedules or single line diagrams, and twelve months of DEWA bills, plus signed paperwork formally identifying your solar contractor, as-built architectural and structural drawings of the building, and the design drawings and calculations prepared for the submission. In leased units the electrical documentation sometimes sat with a previous tenant, and retrieving it late causes long delays.
Can I install solar on my roof without the landlord's involvement? In a leased unit you will generally need the landlord's agreement, since the application relies on the plot's electrical connection documentation and the system is a long-term fixture on their building. It is worth raising early, alongside how the remaining lease term compares with the system's payback period.
Should I fix my roof before or after installing solar? Before. Once an array is in place, any remedial work to the roof underneath means removing and reinstating the panels, which is a significant cost and a risk to both the array and the mounting penetrations. A roof assessment at feasibility stage establishes whether the roof needs work, and doing it first costs far less than doing it later.